October 2026

Following the dedication of the 5/31 Memorial in May, the City of Virginia Beach continues to make progress on the remaining improvements to the memorial grounds. Several important elements have recently been completed, including the fabrication and installation of the permanent drainage grate surrounding the fountain and the completion of the mulch pathways through the wooded area.

Work is also underway on the concrete pathways around the pond and improvements to the parking lot. These elements, along with the majority of the remaining project work, are anticipated to be completed by mid-November 2026. The tree lighting is currently in fabrication and is expected to be installed by mid-January 2027.

While the dedication marked an important milestone, the City remains committed to completing these final improvements with the care and attention this meaningful space deserves. We look forward to sharing additional progress as the remaining work is completed.

February/March 2026

During the months of February and March, construction on the Virginia Beach 5/31 Memorial has achieved several significant milestones. Waterproofing and the stone installation at the fountain is nearing completion. Following the installation of the fountain stone, fine grading and pavers will be installed. Additionally, the stone installation at the life walls, hero stone, and name wall is underway. Construction will continue to progress in the Survivor’s Grove and glade area. Metal siding for the pump house was completed, which allows the electrical panels and various other utility equipment to be installed. Once the utility equipment is installed, the electrical start-up will commence.

November/December 2025

During the November and December update period, construction on the Virginia Beach 5/31 Memorial has achieved several significant milestones. The structural foundation for the water feature is well underway, with the concrete walls, trenches, and steel framing now complete. Additionally, the electrical systems for lighting are currently being installed, and final utility connections are being made to the fountain. The pump house systems are also approaching completion, while fabricated stone panels are being shipped to the site following the initiation of a stone mock-up. Work has also begun on the foundations and walls for the front entry.

May 2025

In May, significant progress was made on the Virginia Beach 5/31 Memorial, with a particular focus on preparing the site for construction. This included securing the designated area at the corner of Princess Anne Road and Nimmo Parkway, establishing a construction trailer, and implementing protective measures for the surrounding trees. The project, aiming for completion by May 2026, is now fully entering its construction phase, with preliminary groundwork and essential site logistics largely addressed.

April 2025

In April, significant steps were taken towards the construction of the Virginia Beach Memorial, honoring the victims of the 2019 mass shooting. While specific detailed updates for April 2025 are limited, the overall project, which is a $14 million investment, has been moving forward with a target completion date of May 2026. This period likely saw continued foundational work and the advancement of elements like the "Survivor's Grove," "Hero Tree," and reflection pool, as outlined in the memorial's design.

March 2025

In March, significant progress was made on the Virginia Beach 5/31 Memorial, with the project moving into its final planning stages before the commencement of construction. Key updates included Dills Architects providing a detailed overview of the memorial's final design, which had been selected in 2023. This presentation was the last step before the physical building process was set to begin.